Day Surgery Centre - Castle Hill Hospital

Type:Health Centre

Client:Humber Teaching NHS Foundation Trust

Status:Phase 1 - Complete / Phases 2 & 3 ongoing

Instruction:Cost Consultant

Location:Cottingham, Hull

Located within Castle Hill Hospital, Cottingham, the new day surgery has been split in to 3 phases for construction:

Phase 1 was completed in early 2023 and Phases 2 & 3 are due to be completed in early 2025.

 

LHL Group are pleased to be assisting the NHS with Cost Consultancy services on this key project and several others at Hull Royal Infirmary.

Read More

3
2
4
pic-3
pic-7
IMG_6483

Phase 1 

Totalling 64,500 sq ft, the £10 million surgery unit includes 4 operating theatres for procedures ranging from facial operations to neurosurgery.

 

Phases 2 & 3

Due for completion early 2025 and will include a further 10 operating theatres 